Renovating the Backup Generator Room

Over the course of 12 months, we stripped the old backup generator room, steam cleaned the walls, re-poured the floor and rewired it.

While Hawklaw was operational, the back-up generator room housed a large diesel generator powerful enough to run the entire station in the event of mains power failing.

Little of the original equipment remained in this room when we bought Hawklaw in 2012 and the room was damp, dirty and a haven for pigeons, mice and even rats.

Step 1 – stripping the room

Although the actual generator was long gone, much of the ancillary fixtures to run it were still evident, including the giant air intake and exhaust. Both of them required a winch to safely lower them down from the roof.

The next issue to tackle was how to remove the raised plinth. This was 12 inch deep, reinforced concrete pad laid on sand and connected to 12 reinforced concrete piles. The reason for such a heavily engineered plinth was to prevent vibrations from the diesel generator vibrating the entire engineer’s garage.

We removed it by first sawing the pad into sections with a stihl saw, then using a Hilti TE1000 heavy duty breaker to remove the sections. This was very dusty and back breaking work.

Removing and rerouting the electrics

Vintage Light Switch
1940’s Crabtree cast
iron light switch

One of the things I love about Hawklaw is figuring out how everything worked and wherever possible, we like to renovate and reuse old things we find for example, this original Crabtree cast iron light switch that we reconditioned and is now in use in our Robin Hood Room.

The key objective was to install modern, ducted electrics in the room, but firstly, I wanted to preserve as many artefacts as I could, and temporarily reroute electrics while some of the other works continued in the room.

We discovered 2 Sangamo timers, connected to lighting circuits which were presumably used to control the exterior lighting on the site. These controls were relatively modern and able to adjust for varying hours of darkness as the seasons changed.

To be continued…

The Tale of the Strimmed Data Cable

I accidentally cut through a 4 core fibre data cable

Strimmed data cable

Earlier this year, I cabled the engineers garage and main buildings together here at Hawklaw. Given the 170m cable run, standard ethernet was out of the question. So, I hurriedly installed a 170m pre-terminated armoured fibre cable. I haven’t yet gotten around to burying the cable, a task that’s been on my to-do list.

Last weekend, while tidying up the area around our chickens, I had an unfortunate mishap. My expensive cable made an unfortunate connection with my scrub cutter. I was faced with replacing the whole run or finding someone who could splice a fibre cable.

Initially, I considered purchasing a fusion splicer to fix it myself. However, with a price tag of £6000, there was no way I could justify the investment for a one-time repair. Hiring one was another option, but that would have taken too long and I didn’t want to be without data between the two buildings for that long.

Luckily, if you live in Fife, you’re only 2 degrees of separation from anyone and this was no exception, luckily, I “kent a boy that kens a boy” (well, it was a girl actually) who had a fusion splicer. This friend of a friend came to the rescue, and with his expertise and the magic of the splicer, he managed to repair the cable. It was a tense moment, but thanks to our helpful community, we were back online in no time!

Splicing OM4 fibre with a fusion splicer.

Lesson learned—I won’t make that mistake again. Stay tuned for more updates from Hawklaw!

The completed compact multi fibre joint. Slight overkill for a 4 core splice.

Now all I need to do is get round to hiring a mini-digger and getting this cable safely underground, where it should be!